The City of Calgary challenges the province's cost estimate for the Green Line LRT, claiming it's $1 billion higher.

The City of Calgary claims the province's revised alignment for the Green Line LRT will cost $7.5 billion, instead of the $6.2 billion previously suggested by provincial officials. City officials said $1.3 billion 'in known costs and risks' were not included in the work by AECOM , the third-party consultant the province hired to find a new downtown alignment. When factoring in those costs, the city believes the province’s proposed alignment from 7 Avenue to Shepard would cost $7.5 billion.

The province previously suggested its proposed alignment, which opts for an elevated route through the downtown core instead of tunnelling and extends at-grade further south to Shepard, could be achieved for $6.2 billion. That is the same budget as the city’s previous alignment, which included a downtown tunnel but only went as far south as Lynwood/Millican with five fewer stops due to cost concerns. However, further details of what is included in the $1.3 billion in 'missing' costs were limited, as AECOM’s report into its alignment remains confidential at the province’s request. 'We’ve been very clear that risk is a very real issue for our city, and we’ve been very clear that we think there’s errors with the numbers,’ Calgary Mayor Jyoti Gondek told reporters. 'We’re trying to be as transparent as we can in indicating what it is we need to discuss further.' Calgary city council spent much of the day Tuesday in a public and confidential briefing and debate over the province’s proposed plan for the Green Line LRT project, which was announced Friday

We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

GlobalCalgary /  🏆 50. in CA

Green Line LRT Calgary Cost Overrun Provincial Alignment AECOM

Canada Latest News, Canada Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

Calgary Council Seeks Urgent Meeting on Revised Green Line LRT PlanCalgary Council Seeks Urgent Meeting on Revised Green Line LRT PlanCalgary city council is pushing for an urgent meeting with the Alberta government to discuss a revised plan for the Green Line LRT project, after the province announced significant changes to the proposal, including cost savings and an elevated downtown track.
Read more »

Calgary Green Line LRT cost soars to $7.5 billionCalgary Green Line LRT cost soars to $7.5 billionThe City of Calgary says the updated Green Line LRT alignment proposed by the Alberta government would cost $7.5 billion, significantly higher than the $6.2 billion estimate provided by the province's consultant.
Read more »

Calgary Council Seeks Urgent Meeting with Alberta Over Green Line LRT PlanCalgary Council Seeks Urgent Meeting with Alberta Over Green Line LRT PlanCalgary city council is pushing for an urgent meeting with the Alberta government to discuss a revised plan for the multibillion-dollar Green Line light rail transit project. The province's updated proposal, announced Friday, includes cost savings and an elevated track downtown, but council members say they need more time to review the details.
Read more »

Calgary Green Line LRT Project Leaves Residents Feeling Ripped OffCalgary Green Line LRT Project Leaves Residents Feeling Ripped OffThe Green Line LRT project in Calgary has faced numerous delays and changes, leaving residents who made sacrifices for the project feeling frustrated and betrayed. The latest proposal from the Alberta government includes a revised alignment and additional stops, but it lacks an Eau Claire station, raising further concerns for affected residents.
Read more »

New Green Line LRT alignment revealed at same $6.2B price tagNew Green Line LRT alignment revealed at same $6.2B price tagThis file photo from September 2024 shows the former Lilydale Chicken Packaging plant in the Southeast community of Ramsay. This is one of the vacant pieces of land held for a future Green Line LRT project.
Read more »

New Green Line LRT alignment expected from province in coming weeksNew Green Line LRT alignment expected from province in coming weeksThis file photo from September 2024 shows the former Lilydale Chicken Packaging plant in the Southeast community of Ramsay, one of the vacant pieces of land held for a future Green Line LRT project.
Read more »



Render Time: 2025-02-15 11:00:52